RECYCLED ENERGY

Vinh Long solar power plant

The Thuan Nhien Phong wind power project will be operated with GE's 3.8 MW turbine, with a rotor diameter of 137 m and a pillar height of 131.4 m, designed to suit wind conditions in Binh Thuan province. .

Central Solar Power Plant - Khanh Hoa

The Central Power Solar Power Plant Project has a total design capacity of 50 MW, located in Cam An Bac commune, Cam Lam district, Khanh Hoa province. The project is about 1,372 billion VND invested by the Central Power Corporation (EVNCPC).

KuJut solar power plant

Duc Hoa 500kV Connecting Substation was built in Hoa Khanh Dong commune, Duc Hoa district, Long An province, invested by the National Power Transmission Corporation (EVNNPT). The station has  1 500kV-900MVA transformer, 6 compartments of 500kV, 7 compartments of 220kV. 

POWER LINE AND STATIONS

Thuan Nhien Phong Wind Power Plant

The Thuan Nhien Phong wind power project will be operated with GE's 3.8 MW turbine, with a rotor diameter of 137 m and a pillar height of 131.4 m, designed to suit wind conditions in Binh Thuan province. .

500kV Quang Trach Doc Soi transmission line

Construction of a 500kV dual-circuit transmission line passing through the territory of 02 provinces of Quang Binh and Ha Tinh with a total length of about 32,6km with starting point is 500kV SPP Quang Trach Power Center and ending point is 500KV Vung Ang substation;

Duc Hoa 500kV substation

Duc Hoa 500kV Connecting Substation was built in Hoa Khanh Dong commune, Duc Hoa district, Long An province, invested by the National Power Transmission Corporation (EVNNPT). The station has  1 500kV-900MVA transformer, 6 compartments of 500kV, 7 compartments of 220kV.