VNECO hit 2 Package, Package Package 6a and DH-3.2-

General JSC Vietnam Electricity Construction (VNE) has won 2 packages: Package No. 6a: Construction line supply line segment from G16 to end and prevent 220kV substation feeders in Phan Thiet, Project: 220kV Vinh Tan-Phan Thiet, 2 circuit 220 kV voltage level, length of 53 km with a value of more than 100 billion (inclusive of 10% VAT). Tender packages DH-3.2: Construction of the station project: Substation 500 / 220kV Coastal ttdl, voltage: 500kV capacity 2x450MVA station, with values close to 155 billion (inclusive of 10% VAT).
Both works have signed the contract and carry out the construction, the construction period is 12 months Package 6a and DH-3.2 package is 15 months from the commencement date.